South Peachtree Creek Trail update

On Friday, June 20, the Oversight Committee of community rep's walked the site with PATH Foundation and county rep's. Concrete segment in Mason Mill was completed, and EPD ok'd removal of silt fences. Boardwalk segment in Medlock was completed; concrete segment was nearly complete. Boardwalk construction had started in Mason Mill. Committee gave top priority to drainage mitigation and slope stabilization. Completion estimated in 45 days.